  1.                          SECTION 10165
  2.  
  3.               PLASTIC LAMINATE TOILET COMPARTMENTS
  4. NOTE ** This section includes plastic laminate toilet
  5.         compartments manufactured by Global Steel Products,
  6.         Inc., headquartered at the following address:
  7. NOTE **     Global Steel Products, Inc.
  8. NOTE **     95 Marcus Blvd.
  9. NOTE **     Deer Park NY 11729-4595
  10. NOTE **     Telephone 516-586-3330
  11. NOTE **     FAX 516-586-3455
  12. NOTE **
  13. NOTE ** SECTION 10165 - PLASTIC LAMINATE TOILET
  14.         COMPARTMENTS, Copyright 1996, The Architect's
  15.         Catalog, Inc.
  16.  
  17. PART 1  GENERAL
  18.  
  19. 1.1 SECTION INCLUDES
  20.  
  21.     A.  Plastic laminate toilet compartments, consisting of:
  22. NOTE ** Delete items below not required for project.
  23.         1.  Floor-mounted overhead-braced toilet compartments.
  24.         2.  Floor-mounted toilet compartments.
  25.         3.  Ceiling-hung toilet compartments.
  26.         4.  Wall-mounted urinal screens.
  27.  
  28.     B.  Compartment installation hardware.
  29.  
  30.     C.  Compartment door hardware.
  31.  
  32. 1.2 RELATED SECTIONS
  33. NOTE ** Delete any sections below not relevant to this
  34.         project; add others as required.
  35.  
  36.     A.  Section 10800 - Toilet, Bath, and Laundry Accessories.
  37. NOTE ** For ceiling hung compartments, structural
  38.         suspension and bracing must be specified in another
  39.         section.  Structural steel, steel channels and
  40.         angles, or "Unistrut" are used.  Wood structure is
  41.         not strong enough.  Identify the section where this
  42.         structure is specified:  Section 05120 - Structural
  43.         Steel, or 05500 - Metal Fabrications.  Delete
  44.         following paragraph if no ceiling hung compartments
  45.         are used.
  46.  
  47.     B.  Section _____ - Structural support for ceiling hung
  48.         compartments.
  49.  
  50. 1.3 SUBMITTALS
  51.  
  52.     A.  Submit under provisions of Section 01300.
  53.  
  54.     B.  Product Data:  Manufacturer's printed literature
  55.         indicating typical panel, pilaster, door, hardware and
  56.         fastening.
  57.  
  58.     C.  Shop Drawings:  Submit six sets of the following:
  59.         1.  Dimensioned plans indicating layout of toilet
  60.             compartments.
  61.         2.  Dimensioned elevations indicating heights of doors,
  62.             pilasters, separation partitions, and other
  63.             components; indicate locations and sizes of openings
  64.             in compartment separation partitions for toilet and
  65.             bath accessories to be installed in partitions;
  66.             indicate floor and ceiling clearances.
  67.         3.  Details indicating anchoring components and methods
  68.             for project conditions; indicate components required
  69.             for installation, but not supplied by toilet
  70.             compartment manufacturer.
  71.  
  72.     D.  Samples:  Two manufacturer's color cards representing
  73.         manufacturer's full color palette.
  74.  
  75. 1.4 DELIVERY, STORAGE AND HANDLING
  76.  
  77.     A.  Store compartment components until installation in
  78.         unopened cartons in vertical position, with adequate
  79.         support to ensure flatness and to prevent damage to
  80.         prefinished surfaces.
  81.  
  82. 1.5 ENVIRONMENTAL REQUIREMENTS
  83.  
  84.     A.  Do not deliver materials or begin construction activities
  85.         of this section until building is enclosed, with complete
  86.         protection from outside weather, and building temperature
  87.         maintained at a minimum of 60 degrees Fahrenheit.
  88.  
  89. 1.6 SEQUENCING
  90.  
  91.     A.  Obtain accessory manufacturer's installation instructions
  92.         and installation templates for toilet and bath
  93.         accessories to be installed in compartment separation
  94.         partitions; supply instructions and templates to
  95.         installer before beginning construction activities of
  96.         this Section.
  97.  
  98. PART 2  PRODUCTS
  99.  
  100. 2.1 MANUFACTURERS
  101.  
  102.     A.  Acceptable Manufacturer:  Global Steel Products, Inc.; 95
  103.         Marcus Blvd., Deer Park NY 11729-4595; telephone 516-586-
  104.         3330, FAX 516-586-3455.
  105. NOTE ** Delete one of the two paragraphs below; coordinate
  106.         with Division 1 requirements.
  107.  
  108.     B.  Substitutions:  Not permitted.
  109.  
  110.     C.  Requests for substitutions will be considered in
  111.         accordance with provisions of Section 01600.
  112.  
  113. 2.2 PLASTIC LAMINATE TOILET COMPARTMENTS
  114. NOTE ** Delete all but one of following three paragraphs;
  115.         Embassy is floor-mounted overhead-braced, Regal is
  116.         floor-mounted, Imperial is ceiling-hung.
  117.  
  118.     A.  Acceptable Product:  Embassy Plastic Laminate Toilet
  119.         Compartments.
  120.  
  121.     B.  Acceptable Product:  Regal Plastic Laminate Toilet
  122.         Compartments.
  123.  
  124.     C.  Acceptable Product:  Imperial Plastic Laminate Toilet
  125.         Compartments.
  126.  
  127.     D.  Panels:
  128.         1.  Nominal thickness:  1 inch.
  129.         2.  Core:  Multiple layers high density particleboard
  130.             conforming to ANSI 208.1, set with water-resistant
  131.             resin binder.
  132.         3.  Edge Banding:  Plastic laminate matching face sheets,
  133.             applied to partition edges before applying face
  134.             sheets.
  135.         4.  Face sheets:  Plastic laminate conforming to NEMA
  136.             LD3, Type GP50, nominal thickness 0.050 inch, applied
  137.             to overlap edges of edge banding laminate.
  138.  
  139.     E.  Pilasters:
  140.         1.  Nominal thickness:  1-1/4 inches.
  141.         2.  Core:  Multiple layers high density  particleboard
  142.             conforming to ANSI 208.1, set with water-resistant
  143.             resin binder.
  144.         3.  Edge Banding:  Plastic laminate matching face sheets,
  145.             applied to partition edges before applying face
  146.             sheets.
  147.         4.  Face sheets:  Plastic laminate conforming to NEMA
  148.             LD3, Type GP50, nominal thickness 0.050 inch, applied
  149.             to overlap edges of edge banding laminate.
  150. NOTE ** Delete one of two paragraphs below; retain first
  151.         paragraph if overhead-braced or floor-mounted
  152.         compartments selected; retain second paragraph if
  153.         ceiling-mounted compartments selected.
  154.         5.  Pilaster installation hardware preparation:  Two
  155.             holes, diameter to accept 3/8 inch threaded rod,
  156.             drilled into core at pilaster base end, parallel to
  157.             pilaster vertical axis, intersecting centerlines of
  158.             two holes, diameter to accept Plug-Loc(tm)
  159.             installation hardware, drilled through pilaster
  160.             perpendicular to pilaster face and 1 inch from
  161.             pilaster base end.
  162.         6.  Pilaster installation hardware preparation:  Two
  163.             holes, diameter to accept 3/8 inch threaded rod,
  164.             drilled into core at pilaster top end, parallel to
  165.             pilaster vertical axis, intersecting centerlines of
  166.             two holes, diameter to accept Plug-Loc(tm)
  167.             installation hardware, drilled through pilaster
  168.             perpendicular to pilaster face and 1 inch from
  169.             pilaster top end.
  170.  
  171.     F.  Doors:
  172.         1.  Nominal thickness:  1 inch.
  173.         2.  Core:  Multiple layers high density particleboard
  174.             conforming to ANSI 208.1, set with water-resistant
  175.             resin binder.
  176.         3.  Edge Banding:  Plastic laminate matching face sheets,
  177.             applied to partition edges before applying face
  178.             sheets.
  179.         4.  Face sheets:  Plastic laminate conforming to NEMA
  180.             LD3, Type GP50, nominal thickness 0.050 inch, applied
  181.             to overlap edges of edge banding laminate.
  182. NOTE ** 18 standard colors are available.
  183.  
  184.     G.  Color and Finish:  Selected from manufacturer's full
  185.         color palette.
  186.  
  187. 2.3 ACCESSORIES
  188.  
  189.     A.  Pilaster Shoes:  Four-piece Type 304 stainless steel
  190.         assembly, No. 4 satin finish, hemmed top and bottom
  191.         edges.
  192.  
  193. NOTE ** Delete one of the two paragraphs below.  The first
  194.         paragraph is for overhead-braced or floor-mounted
  195.         compartments, the second paragraph is for ceiling-
  196.         hung compartments.
  197. NOTE **
  198. NOTE ** Floor-mounting requires a concrete floor for
  199.         adequate anchorage.
  200. NOTE ** Ceiling-mounting requires steel structure for
  201.         adequate support.
  202.  
  203.     B.  Pilaster Anchors:  Manufacturer's standard floor
  204.         anchoring system with leveling adjustment, concealed by
  205.         pilaster shoe after installation.
  206.  
  207.     C.  Pilaster Anchors:  Manufacturer's standard ceiling
  208.         anchoring system with leveling adjustment, concealed by
  209.         pilaster shoe after installation.
  210. NOTE ** Delete paragraph below if urinal screens not
  211.         required.
  212.  
  213.     D.  Urinal Screen Brackets:  Full height 38-inch-long two ear
  214.         anodized aluminum with satin finish, prepared for
  215.         fastening hardware.
  216. NOTE ** Delete paragraph below if overhead-braced
  217.         compartments are not required.
  218.  
  219.     E.  Head Rail:  Manufacturer's standard anodized aluminum
  220.         rail with anti-grip device.
  221. NOTE ** Delete one of the following two sets of paragraphs
  222.         on brackets and hardware.
  223.  
  224.     F.  Brackets:  Heavy duty, die-cast non-ferrous chrome-
  225.         plated, with chrome-plated throughbolts and fasteners
  226.         with tamper-resistant heads.
  227.  
  228.     G.  Door Hardware:  Heavy duty, die-cast non-ferrous chrome-
  229.         plated.
  230. NOTE ** Stainless steel brackets and hardware are an extra
  231.         cost option.
  232.  
  233.     H.  Brackets:  Die-cast No.304 stainless steel, No.4 satin
  234.         finish, with throughbolts and fasteners of same material
  235.         and finish with tamper-resistant heads.
  236.  
  237.     I.  Door Hardware:  Die-cast No.304 stainless steel, with
  238.         No.4 satin finish.
  239. NOTE ** The following sub-paragraphs apply to both types of
  240.         hardware.
  241.         1.  Top and Bottom Hinges:  Recessed into door with
  242.             saddle on adjacent pilaster, providing bi-directional
  243.             operation about axis within the plane of the door;
  244.             adjustable cams supporting door, returning to resting
  245.             position by gravity.
  246.         2.  Latch:  Door-mounted slide latch.
  247.         3.  Stop and Keeper:  Permitting emergency access by
  248.             lifting the door until latch is clear of keeper.
  249.         4.  Coat Hook:  Black rubber tip for door stop.
  250. NOTE ** Delete one of the two paragraphs below.  The first
  251.         paragraph is for non-ferrous hardware; the second
  252.         paragraph is for stainless steel hardware.
  253.         5.  Fastening Hardware: Chrome-plated through-bolts and
  254.             attachment fasteners with tamper-resistant heads.
  255.         6.  Fastening Hardware:  Stainless steel with No.4 satin
  256.             finish, through-bolts and attachment fasteners with
  257.             tamper-resistant heads.
  258.  
  259.     J.  Toilet and Bath Accessories for Installation in
  260.         Compartment Separation Partitions:  Specified Section
  261.         10800.
  262.  
  263. PART 3  EXECUTION
  264.  
  265. 3.1 EXAMINATION
  266.  
  267.     A.  Verification of Conditions:
  268.         1.  Measure areas to receive compartments; verify area
  269.             dimensions are in accordance with shop drawings.
  270.         2.  Verify built-in framing, anchorage, bracing, and
  271.             plumbing fixtures are in correct location.
  272.  
  273.     B.  Installer's Examination:
  274.         1.  Have installer of this section examine conditions
  275.             under which construction activities of this section
  276.             are to be performed, then submit written notification
  277.             if such conditions are unacceptable.
  278.         2.  Transmit two copies of installer's report to
  279.             Architect within 24 hr of receipt.
  280.         3.  Beginning construction activities of this section
  281.             before unacceptable conditions have been corrected is
  282.             prohibited.
  283.         4.  Beginning construction activities of this section
  284.             indicates installer's acceptance of conditions.
  285.  
  286. 3.2 PREPARATION
  287.  
  288.     A.  Surface Preparation:
  289.         1.  Prepare openings in compartment separation partitions
  290.             for toilet and bath accessories to be installed in
  291.             partitions; marring of partition finish is
  292.             prohibited.
  293.         2.  Locate openings in accordance with shop drawings and
  294.             accessory manufacturer's installation instructions
  295.             and templates.
  296.  
  297. 3.3 INSTALLATION
  298.  
  299.     A.  Install compartments to specified tolerances in
  300.         accordance with shop drawings and manufacturer's printed
  301.         installation instructions.
  302.  
  303.     B.  Attach components to adjacent materials and to other
  304.         components using purpose-designed fastening devices.
  305. NOTE ** Delete one of two paragraphs below.
  306.  
  307.     C.  Adjust pilaster anchors for floor variations; conceal
  308.         anchors with pilaster shoes.
  309.  
  310.     D.  Support pilasters from above ceiling framing using two
  311.         adjustable hanging studs for vertical adjustment to
  312.         level; conceal ceiling fastenings with pilaster shoes.
  313. NOTE ** The remaining provisions apply to all types of
  314.         compartments in this section.
  315.  
  316.     E.  Equip each compartment door with top and bottom hinges,
  317.         and door latch.
  318.  
  319.     F.  Install door strike keeper on pilasters in alignment with
  320.         door latch.
  321.  
  322.     G.  Equip each compartment door with one coat hook and
  323.         bumper.
  324.  
  325.     H.  Installation Tolerances:
  326.         1.  Max. variation from plumb or level:  1/8 inch.
  327.         2.  Max. displacement from indicated position:  1/8 inch.
  328.         3.  Clearance between wall surface and panels or
  329.             pilasters:  1-1/2 maximum.
  330.  
  331. 3.4 ADJUSTING
  332.  
  333.     A.  Adjust door hardware for uniform clearance between doors
  334.         and pilasters.
  335.  
  336.     B.  Adjust door hinges to attain free movement, to locate
  337.         in-swinging doors in partial open position when
  338.         unlatched; and to return out-swinging doors to closed
  339.         position.
  340.  
  341.     C.  Adjust door hardware to align door strike keeper on each
  342.         pilaster with door latch.
  343.  
  344. 3.5 PROTECTION OF INSTALLED PRODUCTS
  345.  
  346.     A.  Prevent damage to product finishes by subsequent
  347.         construction activities.
  348.  
  349.     B.  Replace components having damaged finish.
  350.  
  351.     C.  Remove factory protective coverings and clean finish
  352.         surfaces in accordance with manufacturer's instructions
  353.         before final inspection.
  354.  
  355. 3.6 SCHEDULE
  356. NOTE ** If more than one type of partition is required, or
  357.         more than one color or finish, a schedule may help
  358.         to the types and where they are to be used.
  359.  
  360.     A.  Men's Toilet Room No. ___:  Floor-mounted overhead-braced
  361.         plastic laminate toilet compartments and wall-mounted
  362.         urinal screens; _______ color, matte finish.
  363.  
  364.     B.  Women's Toilet Room No. ___:  Ceiling-hung plastic
  365.         laminate toilet compartments; compartment separation
  366.         partitions _______ color, matte finish; pilasters _______
  367.         color, matte finish; doors to match compartment
  368.         separation partitions.
  369.  
  370.                          END OF SECTION